Skip to Content
Menu
Home
Residences
Amenities
Virtual Tour
The Views
Watch Videos
Work progress
Schedule a Call
Eng
Spanish
WORK PROGRESS
2022 - 2023
100
NOV - JAN
Phase 1
100
Breaking ground
Box excavation
Pile casting
FEB - APR
Phase 2
100
Assembled leagues
Foundation basis
Retaining walls
MAY - JUL
Phase 3
100
Reinforced basement slab
Formwork and casting of slab in basement
AUG - OCT
Phase 4
90
First level walls
Assembly and cast of first level slab
2023 - 2024
80
NOV - JAN
Phase 5
100
Second level walls
Assembly and cast of second level slab
FEB - APR
Phase 6
90
Third level walls
Assembly and cast of third level slab
MAY - JUL
Phase 7
90
Fourth level walls
Assembly and cast of fouth level slab
AUG - OCT
Phase 8
60
Fifth level walls
Assembly and cast of fifth level slab
2024 - 2025
5
NOV - JAN
Phase 9
10
Sixth level walls
Assembly and cast of sixth level slab
FEB - JUN
Phase 10
Ground floor finishes
First floor finishes
Second floor finishes
Third floor finishes
Fourth floor finishes
Condos fully finished